About this project
As a part of an annual rehabilitation program, the Parks and Open Space Department has had inspections of all bridge and stair structures conducted to determine any required works.
The structures included in this current project were identified as requiring replacement, mostly because they did not meet current Town standards or were at the end of their design life.
Along with structural replacements, sections of trails and landscaping may be updated or upgraded simultaneously.
The sites and their respective works include:
Glen Oak Creek Trail
The existing wooden pedestrian bridge will be replaced with a manufactured steel bridge.
Phase 1: Completed and re-opened to public.
Indian Ridge Trail
The existing double culverts will be replaced with a manufactured steel bridge.
Phase 1: Completed and re-opened to the public.
McCraney Valley Park
The existing culvert will be replaced with a manufactured steel pedestrian bridge.
Phase 1: Completed and re-opened to the public.
Petro-Canada Park
The existing wooden boardwalk will be replaced with a new one. A retaining wall will be added to address an erosion issue as well as landscape treatment at the adjacent hill.
Phase 1: Completed and re-opened to the public.
Fisherman’s Wharf
The existing wooden boardwalk will be replaced with a wider boardwalk.
Phase 2: Completed and re-opened to the public.
Iroquois Shoreline Woodlot
The existing small wooden pedestrian bridge will be replaced with a new one.
Phase 2: Completed and re-opened to the public.
Morrison Valley South
The existing stair structure will be replaced with a new one.
Phase 2: Completed and re-opened to the public.
Pondview Place
The existing wooden elevated boardwalk will be replaced with a new one.
Phase 2: Completed and re-opened to the public.
Sixteen Mile Creek – boardwalk
The existing boardwalk will be replaced with a new one. The scope of work may also include creek realignment.
Phase 2: Completed and re-opened to the public.
Abourview Trail
The two existing manufactured steel pedestrian bridges will be replaced with new ones.
Phase 3: To be tendered in March/April 2025. Anticipated completion by December 2025.
Sixteen Mile Creek – staircase
The extra-large staircase structure is scheduled for repairs/replacement.
Phase 3: To be tendered in March/April 2025. Anticipated completion by December 2025.
Consultant/contractor
Moon-Matz Limited has been retained for design work and contract administration.
Phase 1 construction: Awarded to Hawkins Construction - fully completed
Phase 2 construction: Awarded to R&M Construction - fully completed
Phase 3: To be tendered at the end of March/early April 2025.
- Parks Directory
- Destination Parks
- Splash Pads
- Sports Fields
- Dog Parks
- Gardens
- Outdoor Courts
- Outdoor Ice Rinks
- Skateboard Parks
-
- Park Planning Projects
- Berta Point West Bank Seawall Improvements
- Bridges, Stairs and Boardwalk replacements
- Bronte Beach Redevelopment
- Coronation Park Playground Renewal
- Crosstown Trail
- McDuffe Park
- Oakville Harbour - West Shore Landscape Master Plan Implementation
- Palermo Park
- Shevchenko Parkette
- Sixteen Mile Creek Heritage Trail Slope Remediation
- Sixteen Mile Sports Complex
- Tennis and Pickleball Court Renewal
- Towne Square
- Trail Accessibility Audit & Strategy
- Wallace Park
Contact
ServiceOakville
905-845-6601