About this project
As a part of an annual rehabilitation program, the Parks and Open Space Department has had inspections of all bridge and stair structures conducted to determine any required works.
The structures included in this current project were identified as requiring replacement, mostly because they did not meet current Town standards or were at the end of their design life.
Along with structural replacements, sections of trails and landscaping may be updated or upgraded simultaneously.
The sites and their respective works include:
Glen Oak Creek Trail
The existing wooden pedestrian bridge will be replaced with a manufactured steel bridge.
Phase 1: Completed and re-opened to public.
Indian Ridge Trail
The existing double culverts will be replaced with a manufactured steel bridge.
Phase 1: Re-opened to public. Planting/seeding to be completed by the end of May 2024.
McCraney Valley Park
The existing culvert will be replaced with a manufactured steel pedestrian bridge.
Phase 1: Bridge installation is completed. Currently re-constructing the asphalt pathway from the walkway block to the new structure. Anticipated completion by the end of April 2024.
Petro-Canada Park
The existing wooden boardwalk will be replaced with a new one. A retaining wall will be added to address an erosion issue as well as landscape treatment at the adjacent hill.
Phase 1: Currently in construction. Anticipated completion at the end of June 2024.
Fisherman’s Wharf
The existing wooden boardwalk will be replaced with a wider boardwalk.
Phase 2: Construction is scheduled to start end of April and is anticipated to be completed by June 2024.
Iroquois Shoreline Woodlot
The existing small wooden pedestrian bridge will be replaced with a new one.
Phase 2: Construction is scheduled to start early May and is anticipated to be completed by June 2024.
Morrison Valley South
The existing stair structure will be replaced with a new one.
Phase 2: Construction is scheduled to start end of May and is anticipated to be completed end of June 2024.
Pondview Place
The existing wooden elevated boardwalk will be replaced with a new one.
Phase 2: Construction is scheduled to start in June and is anticipated to be completed early August 2024.
Sixteen Mile Creek – boardwalk
The existing boardwalk will be replaced with a new one. The scope of work may also include creek realignment.
Phase 2: Construction is scheduled to start end of June and is anticipated to be completed early August 2024.
Abourview Trail
The two existing manufactured steel pedestrian bridges will be replaced with new ones.
Phase 3: In design stage.
Sixteen Mile Creek – staircase
The extra-large staircase structure is scheduled for repairs/replacement.
Phase 3: In design stage. Anticipated completion by December 2024.
Consultant/contractor
Moon-Matz Limited has been retained for design work and contract administration.
Phase 1 construction: Awarded to Hawkins Construction
Phase 2 construction: Awarded to R&M Construction
Phase 3: To be determined.
- Parks Directory
- Destination Parks
- Splash Pads
- Sports Fields
- Dog Parks
- Gardens
- Outdoor Courts
- Outdoor Ice Rinks
- Skateboard Parks
-
- Park Planning Projects
- Aspen Forest Park Proposed Splash Pad
- Berta Point West Bank Seawall Improvements
- Bridges, Stairs and Boardwalk replacements
- Bronte Beach Redevelopment
- Bronte Inner and Outer Harbour Dredge
- Coronation Park Playground Renewal
- Crosstown Trail
- George Savage Park All-Season Sport Court
- McDuffe Park
- Oakville Harbour - West Shore Landscape Master Plan Implementation
- Palermo Park
- Shevchenko Parkette
- Sixteen Mile Creek Heritage Trail Slope Remediation
- Sixteen Mile Sports Complex
- Tennis and Pickleball Court Renewal
- Towne Square
- Trail Accessibility Audit & Strategy
- Wallace Park
- Wynten Way Park Splash Pad & Playground Replacement
Contact
ServiceOakville
905-845-6601